Home    Contact Us    A A A

Case Study: University of the Arts, London SW1

University of the arts 

Client
University of the Arts

Location
16 John Islip Street, Pimlico, London, SW1P 4JU

Scheme Details
On the 21st December 2007 Blakedown Landscapes (SE) Limited where appointed to begin work converting the University Of the Art’s existing parade ground into an outdoor art gallery. The new gallery is Europe’s largest outdoor gallery, billed as a ‘Gallery without walls’. The agreed Contract Sum is £1,269,742.09, but was subsequently later reduced by the client. The job was delayed by 2 weeks whilst on site due to design alterations but was delivered under budget by circa £10k.
 
Fit Out Project Value
£1,168,735.90 Agreed Final Account

Procurement
The project was procured on a JCT Standard Building Contract without Quantities (SBC/XQ)

Millbridge Role
Quantity Surveyor

Timescale
January 2008 - completion June 2008

« Back to project page