Client: International Finance Corporation World Bank Group
Sector: Offices & Headquarters
Services: Cost Management & Building Surveying
Project Brief:

We provided Cost Management Services for the interior fit-out of approximately 3,000sq ft of office space on the 20th floor of the Millbank Tower in London.

The construction cost was circa £500k and the period on site was 12 weeks utilising a client bespoke form of building contract, including careful liaison with the landlord to ensure all of their and adjoining tenants’ needs and requirements were met during the construction process.